Project Location General Contractor Owner Architect Date Completed
INSTALL GIANT VOICE SYSTEM, KEESLER AIR FORCE BASE BILOXI, MS McClain Contracting US Air Force Civil Engineering – Keesler December,2009
LOGISTICS WAREHOUSE, NAVAL CONSTRUCTION BATTALION CENTER GULFPORT, MS BE&K Government Group Dept. of the Navy BRPH Architects, Engineers December,2009
VARIOUS BUILDINGS, NAVAL CONSTRUCTION BATTALION CENTER GULFPORT, MS Roy Anderson Corp. Naval Fac. Eng. Command Studio South Architects December,2009
DOWNTOWN LIGHTING HATTIESBURG, MS Doleac Electric Co., Inc. City of Hattiesburg Shows Dearman Waits December,2009
ONCOLOGY CLINIC, KEESLER AIR FORCE BASE BILOXI, MS Carothers Construction So Div Naval Facilities Rogers, Locelock & Fritz, Inc. November,2009
NEW BASEBALL FIELD LIGHTING FOR PETAL HIGH SCHOOL PETAL, MS Chris Allbritton Petal School District Landry & Lewis Architects, P.A. October, 2009
PINEY WOODS PELLET MILL WIGGINS, MS Northern Electricians, Inc. Tomorrow’s Energy Construction Management, LLC July, 2009
NORTH/NORTH BUILD, NORTHROP GRUMMAN PASCAGOULA, MS Roy Anderson Corp. Northrop Grumman Burk-Kleinpeter, Inc. July, 2009
PROPULSION ASSEMBLY BLDG., NORTHROP GRUMMAN PASCAGOULA, MS Ben M. Radcliff, Inc. Northrop Grumman Burk-Kleinpeter, Inc. May, 2009
WEST BAY 6 & 7, NORTHROP GRUMMAN PASCAGOULA, MS Robert J. Baggett, Inc. Northrop Grumman Burk-Kleinpeter, Inc. April, 2009
WOLFE HALL, KEESLER AIR FORCE BASE BILOXI, MS McClain Contracting So Div Naval Facilities Civil Engineering – Keesler April, 2009
POPPS FERRY BRIDGE BILOXI, MS Joe McGee Construction MS Dept of Transportation Neel Schaffer March, 2009
OCEAN SCIENCE LABORATORY STENNIS SPACE CENTER, MS Roy Anderson Corp. Naval Fac. Eng. Command Studio South Architects March, 2009
OAK GROVE NEW MULTI PURPOSE BUILDING HATTIESBURG, MS C. Perry Builders Lamar County School District Landry & Lewis Architects, P.A. February, 2009
HOOTER’S BILOXI, MS Roy Anderson Corp. RW Development National Restaurant Designers December,2008
GENERATOR FOR BLDG 9101 STENNIS SPACE CTR, MS Orion Services, Inc. US Army Corp of Eng. Burgess & Niple November,2008
CITIZEN’S BANK / BELLEVUE HATTIESBURG, MS Mac’s Construction Co., Inc. Citizen’s Bank Zito Russell Architects, P.A. November, 2008
PROVISION LIVING HATTIESBURG, MS  Pioneer Construction Services of TN Hattiesburg Retirement Investors Sunset Design Services, Inc. November,2008
NICHOLSON & CO., INC. HATTIESBURG, MS Finlo Construction Co., Inc. Nicholson & Co., Inc. Albert & Assoc. of Hattiesburg November,2008
HOSPITAL DOORS, KEESLER AIR FORCE BASE BILOXI, MS Pratt Landry & Associates So Div Naval Facilities URS Group, Inc. October, 2008
BUILDING 9101 RENOVATIONS STENNIS SPACE CTR, MS Whitesell/Yates US Army Corp of Eng. Burgess & Niple September,2008
BUILDING 1000 RENOVATIONS STENNIS SPACE CTR, MS Roy Anderson Corp. MSAAP Schmidt Dell Associates September,2008
NEW AIR CARGO FACILITY GULFPORT, ms Roy Anderson Corp. Gulfport/Biloxi Regional Airport Gresham, Smith & Partners August, 2008
PANEL LINE EXTENSION, NORTHROP GRUMMAN PASCAGOULA, MS Roy Anderson Corp. Northrop Grumman Burke-Kleinpeter, Inc. July, 2008
TECH TRAINING PHASE III, KEESLER AIR FORCE BASE BILOXI, MS Walton Construction So Div Naval Facilities VOA Associates, Inc. June, 2008
NCCIPS – PHASE 2A & 2B STENNIS SPACE CTR, MS Roy Anderson Corp. SAIC Schmidt Dell Associates May, 2008
PELICAN CAY CONDOS BILOXI, MS Carl Woodward Homeowners Assoc. Allred-McNabb May, 2008
SAFEGUARD STEEL HOMES HATTIESBURG, MS Doleac Electric Co., Inc. North-South Properties Henry C. Martin Consultant April, 2008
SO MS ELEC POWER ASSOC. HATTIESBURG, MS Larry J. Sumrall Contractors, Inc. So MS Elec Power Assoc Landry & Lewis Architects, P.A. April, 2008
WATERS INTERNATIONAL HATTIESBURG, MS Finlo Construction Co., Inc. Waters Brothers Partnership Landry & Lewis Architects, P.A. March, 2008
2nd & 3rd FLOOR PATIENT ROOM – RENOV HATTIESBURG, MS DC General Contractors Wesley Medical Ctr Richard L. Miller March, 2008
OWENS-ILLINOIS PRODUCTION EQUIP HATTIESBURG, MS Doleac Electric Co., Inc. Owens-Illinois 0 February, 2008
PETE TAYLOR FIELD SKYBOX & PRESS BOX RENOV & ADDS HATTIESBURG, MS DC General Contractors Univ. of So. MS JH&H Arch/Planners/Int February, 2008
HILTON GARDEN INN HATTIESBURG, MS Journeyman Construction, LP Ramkrupa of America, Inc. David Carter & Associates December, 2007
OAK GROVE ELEMENTARY HATTIESBURG, MS Mac’s Construction Co., Inc. Lamar County School District Landry & Lewis Architects, P.A. November, 2007
SACRED HEART CAFETERIA BUILDING & CLASSROOMS HATTIESBURG, MS Finlo Construction Co., Inc. Roman Catholic Diocese Albert & Assoc. of Hattiesburg October, 2007
NEW ELEMENTARY SCHOOLS FOR SUMRALL, PURVIS, & OAK GROVE  SUMRALL, PURVIS, & OAK GROVE, MS Mac’s Construction Co., Inc. Lamar County School District Landry & Lewis Architects, P.A. October, 2007
CADET POINT SENIOR VILLAGE BILOXI, MS GM&R Construction Biloxi Housing Authority Genzer & Dodds September,2007
WOMEN’S CENTER HATTIESBURG, MS Marshall Erdman & Assoc., Inc. Hattiesburg Clinic Marshall Erdman & Assoc., Inc. June, 2007
CANDLEWOOD SUITES HATTIESBURG, MS Sun Real Estate, LLP Gateway Lodging Associates Zivic & Hurdle June, 2007
EDUCATION BLDG & SANCTUARY WEST CAMPUS HATTIESBURG, MS Mac’s Construction Co., Inc. Temple Baptist Church Landry & Lewis Architects, P.A. May, 2007
NEW DISTRICT HEADQUARTERS BLDG, MS DOT HATTIESBURG, MS Mac’s Construction Co., Inc. MS Dept of Transportation Canizaro Cawthon Davis April, 2007
PEDESTRIAN & BICYCLE IMPROV PLAN/PHASE I HATTIESBURG, MS Maples Construction MS Bureau of Bldg & Grounds The Walker Associates, Eng April, 2007
PHASE IX – POST PARTUM BUILD OUT HATTIESBURG, MS C. Perry Builders Forrest General Hospital Nix Mann Perkins & Will PLLC February, 2007
PEPSI – COLA HATTIESBURG, MS Finlo Construction Co., Inc. Brown Bottling Group Johnson Bailey Henderson McNeel December, 2006
NORTHROP GRUMMAN KATRINA REPAIRS PASCAGOULA, MS Doleac Electric Co., Inc. Northrop Grumman Design Build December, 2006
KATRINA REPAIRS, KEESLER AIR FORCE BASE BILOXI, MS Whitesell/Yates So Div Naval Facilities Design Build September,2006
KATRINA REPAIRS STENNIS SPACE CTR, MS Whitesell/Yates So Div Naval Facilities Schmidt Dell Associates September,2006
ANG FIELD MAINT SHOP GULFPORT, MS Worsham Bros. MS Military Department AE Design Group September,2006
KATRINA REPAIRS – MISSISSIPPI PHOSPHATES PASCAGOULA, MS Doleac Electric Co., Inc. MS Phosphates Corp. Design Build September,2006
4160 V. SHORE POWER BERTH, NORTHROP GRUMMAN PASCAGOULA, MS Robert J. Baggett, Inc. Northrop Grumman Burk-Kleinpeter, Inc. October, 2006
NCCIPS – PHASE I STENNIS SPACE CTR, MS Roy Anderson Corp. SAIC Schmidt Dell Associates June, 2006
DORMITORY & MINI BX, KEESLER AIR FORCE BASE BILOXI, MS Whitesell/Yates So Div Naval Facilities 0 May, 2006
CAMP SHELBY REGIONAL MILITARY CENTER, PHASE III CAMP SHELBY, MS Mac’s Construction Co., Inc. Camp Shelby Barlow, Eddy, Jenkins, P.A. January, 2006
WESLEY MEDICAL E.R. RENOVATIONS & ADDITIONS HATTIESBURG, MS Robbins & Morton Triad Hospital Michael L. Mill May, 2006
WESTERN CONTAINER HYBRID PROJECT HATTIESBURG, MS Doleac Electric Co., Inc. Western Container, Corp. Prime February, 2006
TURTLE CREEK CROSSING HATTIESBURG, MS EMJ Corporation Kimico Hattiesburg LP Winkelmann & Associates, Inc. April, 2006
GRAND THEATER HATTIESBURG, MS Mapp Construction EFT Down Reit, Inc. Beck Architecture November, 2005